Transport · MRT and LRT guide

New MRT lines and stations, in date order

Every opening LTA has announced, from 26 December 2026 to the late 2030s, with the stations in each stage and where each date comes from.

Singapore's rail network is still growing. Between now and the late 2030s, LTA has announced two new lines, extensions of three existing ones, several in-fill stations and a cross-border link. This article puts every one of them in date order, with the stations involved and the source for each target. Dates for large rail works can move, so each entry names the announcement it comes from; LTA's project pages carry the current dates. For where the new stations sit, see the dashed lines and rings on our network map.

The timeline at a glance

TargetProjectStationsSource
26 December 2026Thomson-East Coast Line Stage 5 (TEL5)Bedok South (TE30), Sungei Bedok (TE31)LTA, 4 November 2026
26 December 2026Downtown Line 3 Extension (DTL3e)Xilin (DT36), Sungei Bedok (DT37)LTA, 4 November 2026
February 2027 (expected)Johor Bahru–Singapore RTS LinkWoodlands North to Bukit ChagarLTA and Malaysia's Ministry of Transport, October 2026
Mid-2028 (around)Jurong Region Line, Stage 1JS1 to JS8 and JW1 to JW2LTA factsheet, 4 March 2026
Date to followJurong Region Line, Stages 2 and 3Stage 2: JE1 to JE7; Stage 3: JS9 to JS12 and JW3 to JW5LTA factsheet, 4 March 2026; the project page lists 2028 for Stage 2 and 2029 for Stage 3
2030Cross Island Line, Phase 1Aviation Park (CR2) to Bright Hill (CR13), twelve stationsLTA
2032Cross Island Line, Phase 2Turf City (CR14) to Jurong Lake District (CR19), six stationsLTA
2032Cross Island Line Punggol ExtensionPasir Ris to Punggol, through Elias and RivieraLTA
2034North-South Line in-fill stationBrickland (NS3A)LTA
2035Downtown Line 2 Extension and Sungei KadutDE1, Sungei Kadut (DE2 and NS6)LTA
Mid-2030sJurong Region Line in-fill stationJS2A, serving TengahLTA
Mid-2030sRail link to Changi Airport Terminal 5Thomson-East Coast and Cross Island line extensionLTA Annual Report 2024/25
Late 2030sCross Island Line, Phase 3Four stations to Gul Circle (CR23)LTA
With the developments around themThomson-East Coast Line stations already builtMount Pleasant (TE10), Marina South (TE21), Founders' Memorial (TE22A)LTA

26 December 2026: TEL5 and DTL3e

On 4 November 2026 LTA announced that two eastern extensions open together on 26 December 2026. The Thomson-East Coast Line's fifth stage runs about 2.1 km from Bayshore to Sungei Bedok, adding Bedok South and Sungei Bedok. The Downtown Line's third-stage extension runs about 2.2 km from Expo to Sungei Bedok, adding Xilin. Sungei Bedok becomes an interchange between the two lines, and Xilin sits inside the Tampines planning area while Bedok South and Sungei Bedok fall inside Bedok. Our TEL5 and DTL3e article covers both extensions in detail.

The Johor Bahru–Singapore Rapid Transit System Link is a cross-border shuttle of about 4 km between Woodlands North and Bukit Chagar in Johor Bahru. In October 2026 LTA and Malaysia's Ministry of Transport said in a joint statement that its operator, RTS Operations Pte Ltd, a joint venture of Prasarana and SMRT, expects passenger service to begin in February 2027, subject to independent safety certification and regulatory approvals, after final system tests and trial runs by 31 December 2026. The link is designed for up to 10,000 passengers an hour in each direction, and passengers will clear both countries' immigration checks once, at departure.

Artist's impression, illustrative only: a future MRT station under construction behind hoardings at dusk
Artist's impression. Illustrative only.

The Jurong Region Line: Stage 1 from mid-2028

The Jurong Region Line is about 24 km long with 25 stations, serving Choa Chu Kang, Tengah, Jurong West, Boon Lay and Jurong East, with a west branch to Peng Kang Hill. LTA's project page lists three stages: Stage 1 in 2028, with ten stations from Choa Chu Kang (JS1) to Boon Lay (JS8) and Gek Poh and Tawas on the west branch; Stage 2 in 2028, with the seven stations of the east branch from Tengah Plantation (JE1) through Jurong East to Pandan Reservoir (JE7); and Stage 3 in 2029, with the four stations to Jurong Pier and three more on the west branch. In a factsheet on 4 March 2026 LTA said Stage 1 would open around mid-2028, instead of the earlier end-2027 timeline, and that it would give further updates on the opening dates of the second and third stages as works progress. An in-fill station, JS2A, between Choa Chu Kang West and Tengah, is targeted for the mid-2030s.

2030 and 2032: the Cross Island Line

The Cross Island Line is LTA's longest new line, about 67 km with 27 stations when complete. Its first phase, about 29 km and twelve stations from Aviation Park to Bright Hill, is targeted for 2030 and links to the existing network at Pasir Ris, Hougang, Ang Mo Kio and Bright Hill. Phase 2, about 15 km and six stations from Turf City through King Albert Park and Clementi to Jurong Lake District, and the Punggol Extension, about 7.3 km and four stations from Pasir Ris to Punggol, are both slated for completion in 2032. Our Cross Island Line article goes through each phase station by station.

2034 and 2035: Brickland and Sungei Kadut

Two in-fill projects in the north-west come next. Brickland (NS3A), a new North-South Line station between Bukit Gombak and Choa Chu Kang, is targeted for 2034; it sits on track already in service, which is why the North-South Line diagram draws it on a solid line. In 2035 the Downtown Line's second-stage extension is targeted to run from Bukit Panjang through a station coded DE1 to Sungei Kadut, where a new interchange will also add Sungei Kadut (NS6) to the North-South Line.

The mid-2030s: JS2A and Terminal 5

Two projects carry a mid-2030s target. On the Jurong Region Line, JS2A is an in-fill station that LTA says will serve future demand in Tengah. At the airport, LTA's annual report for 2024/25 lists an extension of the Thomson-East Coast and Cross Island lines to Changi Airport Terminal 5; our Changi Airport by MRT article explains how the airport is reached by rail today.

The late 2030s: Cross Island Line Phase 3

The third phase of the Cross Island Line extends it west from Jurong Lake District with four stations, ending at Gul Circle on the East-West Line. LTA said in March 2026 that construction starts in 2027 and that the phase is slated for completion in the late 2030s. LTA lists three of its stations by code only, CR20, CR21 and CR22.

Stations that open with their surroundings

Three stations on the Thomson-East Coast Line open with the developments around them: Mount Pleasant (TE10), Marina South (TE21) and Founders' Memorial (TE22A). LTA ties their opening to that development rather than to a year. They sit on track already in service, so the line runs past them today.

Studies without opening dates

LTA's factsheet of 4 March 2026 also named three studies that start this year, none with an opening date: a West Coast Extension of the Jurong Region Line from Pandan Reservoir (JE7) to the Cross Island Line's West Coast station (CR18, a working name); a Seletar Line, studied first for a corridor serving Sengkang West and Serangoon North; and a Tengah Line. These are studies rather than projects with targets, so they do not appear on our map.

What the timeline means for neighbourhoods

The new stations reach some neighbourhoods for the first time. Tengah, home to 34,340 residents in June 2026 on SingStat's count, has no station today and gains its first with the Jurong Region Line. Bukit Timah, Clementi, Pasir Ris, Hougang, Serangoon and Ang Mo Kio gain Cross Island Line stations, and Bedok and Tampines gain stations in December 2026. Each guide lists its announced stations with LTA's target, and our stations by planning area table shows them for every area.

Frequently asked questions

What is the next MRT opening?

On 26 December 2026, Bedok South and Sungei Bedok on the Thomson-East Coast Line and Xilin and Sungei Bedok on the Downtown Line.

When does the Jurong Region Line open?

LTA's project page lists 2028 for Stages 1 and 2 and 2029 for Stage 3. In March 2026 LTA said Stage 1 would open around mid-2028 and that it would update the dates for Stages 2 and 3.

When does the Cross Island Line open?

Phase 1 is targeted for 2030, Phase 2 and the Punggol Extension for 2032, and Phase 3 for the late 2030s.

Will there be an MRT to Terminal 5?

LTA's annual report for 2024/25 lists an extension of the Thomson-East Coast and Cross Island lines to Terminal 5 for the mid-2030s.

Will Tengah get an MRT station?

Yes. Tengah has none today; the Jurong Region Line adds Tengah (JS3), Tengah Plantation (JE1) and Tengah Park (JE2), and LTA targets the mid-2030s for the in-fill station JS2A.

Which stations open with the developments around them?

Mount Pleasant (TE10), Marina South (TE21) and Founders' Memorial (TE22A) on the Thomson-East Coast Line. LTA gives no year for them; they open as the areas around them are developed.

LTA and Malaysia's Ministry of Transport said in October 2026 that passenger service is expected to begin in February 2027, subject to safety certification and regulatory approvals.

Sources

  • Land Transport Authority, news release of 4 November 2026 on TEL5 and DTL3e, with route lengths.
  • Land Transport Authority, Factsheet: The Next Phase of Rail Development (4 March 2026).
  • Land Transport Authority, Jurong Region Line and Cross Island Line project pages; Annual Report 2024/25.
  • Land Transport Authority, announcements on Brickland (NS3A) and the Downtown Line 2 Extension.
  • Land Transport Authority and Malaysia's Ministry of Transport, RTS Link update, October 2026.
  • Singapore Department of Statistics, resident population by planning area, June 2026.